Hess Corporation Beaver Lodge Silurian Unit

EAPC provided process engineering and detailed engineering to design a new NGL off-load station with NGL processing and storage. The new NGL system allowed for third party operators to off-load NGL at the site, where it was then processed and pumped to the main gas plant for further treatment.

Concrete foundations were installed to support the new off load storage tanks. Pipe stress analysis was performed for the new piping per ASME B31.3. PSV relieving capacity was calculated in accordance with API and NFPA codes. Piping and structural were modeled in 3D and piping isometrics were generated complete with bills of materials.

EAPC provided process, mechanical, structural, and electrical engineering and design, prepared and distributed bid packages, and received and evaluated bids from contractors.